TCN gives the reason for the reduction in power generation

0 152

The Transmission Company of Nigeria (TCN) has announced that there was a reduction in power generation as a result of gas supply challenges.

In a statement issued on Saturday, TCN’s General Manager, Public Affairs, Ndidi Mbah, explained that there was an emergency maintenance by Nigerian Gas Company (NGC) on pipeline supplying gas to Egbin, Omotosho, Olorunsogo and Paras power stations.

The maintenance, which resulted in the total shutdown of the four power generating plants on April 25, was necessitated by leakage discovered on the Escravos-Lagos gas Pipeline System.

Mbah also said that prior to the incident, Omotosho National Integrated Power Plant (NIPP) and Olorunsogo NIPP were already out due to gas supply issues.

READ ALSO: Nigerian Senators Branded As Nigeria’s Problem,Senator Shehu Lambasted For Criticizing Buhari Over the State of Refinery.

She, however, said NGC had begun works to repair the gas pipeline and restore normal supply to the affected power plants.

“Presently, repairs have been completed and the pipeline is currently being pressurised prior to resumption of gas supply to the affected power stations”, it said.

TCN further noted that it has diverted about 312MW load from the Benin-Egbin 330kV transmission line which tripped at 23.14hours on Tuesday, 23rd April, 2019, to Omotosho –Ikeja West and Ayede-Ikeja 330kV transmission lines, due to on-going repair works on the Benin-Egbin 330kV transmission line.

“The tripping was caused by a line cut between Ofofu and Okada Towns, however TCN engineers are making concerted efforts to complete repair work on the transmission line, despite the very difficult terrain at that location.

“Due to the diversion of the load from this line to the two transmission lines equally feeding Lagos axis, load shedding in Lagos axis was minimised to about 280MW at the first instance.

“However with the attendant gas supply issues and sudden gas leakage problem, load shedding increased considerably.

“TCN regrets inconveniences and wish to assure Nigerians that power supply would return to normal as soon as normal gas supply is restored to the affected power stations and transmission repair work is completed”, the statement added